PRELIMINARY · PERMIT ISSUED

Tentative start: December 1, 2026

Current status: SBA Loan documentation preparing.

10 calendar-week planning window · December 1, 2026–February 5, 2027. Mobilization remains conditional on financing, deposit and notice to proceed.

Holiday allowance: no field work December 24–January 3. No separate two-week shutdown is added. Confirm crew and inspection availability before committing dates.

Drawing basis: 27104 NW Freeway, Suite 109, Cypress · ARC-MPE binder, July 16, 2026 with September 3 revisions. Tasks reference D-101, A-101/102/103/201, I-101/401–403, M100/101/201 and E100/101/200. Verify against the issued permit set.

PRELIMINARY FIELD PLAN

Today on Site

Scheduled activityLoading today’s schedule…
Trades involved—
Coming next—
Baseline turnoverFEB 5, 2027CO / owner handoff
Schedule10 WEEKSIncludes holiday allowance
Tasks complete0 / 37Tracked activities
Next hold pointSBA + DEPOSITRequired before mobilization
PRELIMINARY SCHEDULE

Preliminary Gantt

Task Progress Green — Completed Blue — In Progress
Activity
DEC 1DEC 11DEC 21DEC 31JAN 10JAN 20JAN 30
KEY MILESTONES

Opening-day path

PRELIMINARY ASSUMPTIONS

Before mobilization

01
Funding and deposit

SBA loan documentation is being prepared; confirm closing, deposit and NTP before mobilization.

02
Holiday shutdown

No field work assumed December 24–January 3; confirm holiday availability.

03
Confirm the working schedule

Confirm HVAC, 80-gallon electric water heater requirements and Kaemark deliveries before mobilization. Drawing notes conflict on existing versus scheduled water heater; resolve before ordering. Existing building is identified as not sprinklered; additional fire-system work only if required by permit/AHJ. Inspection labels and dates are planning allowances, not booked appointments.