Tentative start: December 1, 2026
Current status: SBA Loan documentation preparing.
10 calendar-week planning window · December 1, 2026–February 5, 2027. Mobilization remains conditional on financing, deposit and notice to proceed.
Holiday allowance: no field work December 24–January 3. No separate two-week shutdown is added. Confirm crew and inspection availability before committing dates.
Drawing basis: 27104 NW Freeway, Suite 109, Cypress · ARC-MPE binder, July 16, 2026 with September 3 revisions. Tasks reference D-101, A-101/102/103/201, I-101/401–403, M100/101/201 and E100/101/200. Verify against the issued permit set.
Today on Site
Opening-day path
Before mobilization
SBA loan documentation is being prepared; confirm closing, deposit and NTP before mobilization.
No field work assumed December 24–January 3; confirm holiday availability.
Confirm HVAC, 80-gallon electric water heater requirements and Kaemark deliveries before mobilization. Drawing notes conflict on existing versus scheduled water heater; resolve before ordering. Existing building is identified as not sprinklered; additional fire-system work only if required by permit/AHJ. Inspection labels and dates are planning allowances, not booked appointments.