Control points
November 6 field completion · November 10 finals
Field work completes Friday, November 6. Electrical final is pending November 9; fire and building finals are pending November 10. Turnover remains subject to approvals and CO issuance. 4-day administrative delay buffer · November 10–14.
Permit BP2026-00001709 checked October 31: electrical rough, mechanical above-ceiling and mechanical final pending November 3; electrical above-ceiling pending November 6. Plumbing final approved October 26. Sprinkler installation November 2–4; planned sprinkler inspection November 5, booking to confirm.
Long-lead fixtures and trade material must remain available to the field.
Target assumes no significant utility or weather delay.