LIVE FIELD UPDATE

Today on Site

Scheduled activityLoading today’s schedule…
Trades involved—
Coming next—
Targeted completionNOV 10Building final / CO target
Client deadlineNOV 144-day administrative delay buffer · November 10–14
Tasks complete0 / 53Detailed activity tracker
Inspection program19 GATESDates aligned with Port Orange permit record
LIVE SCHEDULE

Opening-day path

Task Progress Green — Completed Blue — In Progress
Activity
AUG 13SEP 1SEP 21OCT 7OCT 27NOV 1NOV 14
KEY INSPECTIONS

Control points

SCHEDULE BASIS

November 6 field completion · November 10 finals

01
Client schedule note

Field work completes Friday, November 6. Electrical final is pending November 9; fire and building finals are pending November 10. Turnover remains subject to approvals and CO issuance. 4-day administrative delay buffer · November 10–14.

02
Scheduled inspections

Permit BP2026-00001709 checked October 31: electrical rough, mechanical above-ceiling and mechanical final pending November 3; electrical above-ceiling pending November 6. Plumbing final approved October 26. Sprinkler installation November 2–4; planned sprinkler inspection November 5, booking to confirm.

03
Material readiness

Long-lead fixtures and trade material must remain available to the field.

04
Utilities and weather

Target assumes no significant utility or weather delay.