Start window: November 15–25, 2026
Pending SBA loan closing and deposit received. Allow 8–10 working weeks, plus the two-week holiday shutdown.
December 20, 2026–January 2, 2027: NO WORK. Work may resume January 3.
The Gantt shows the conservative November 25 start / 10-week working-duration baseline, targeting February 16, 2027. Depending on the actual start and duration, preliminary completion falls January 23–February 16, 2027. Trade dates and inspections are provisional.
PRELIMINARY FIELD PLAN
Today on Site
Scheduled activityLoading today’s schedule…
Trades involved—
Coming next—
Task Progress
Green — Completed
Blue — In Progress
Activity
NOV 15NOV 28DEC 12DEC 25JAN 8JAN 21FEB 4
KEY MILESTONES
Opening-day path
PRELIMINARY ASSUMPTIONS
Before mobilization
01
Funding and deposit
Start remains conditional on SBA loan closing and deposit received.
02
Holiday shutdown
No field work or inspections from December 20 through January 2 inclusive.
03
Confirm the working schedule
Finalize trade availability, deliveries and inspection appointments when the start date is confirmed. The permit is issued.