PRELIMINARY · PRE-MOBILIZATION

Start window: November 15–25, 2026

Pending SBA loan closing and deposit received. Allow 8–10 working weeks, plus the two-week holiday shutdown.

December 20, 2026–January 2, 2027: NO WORK. Work may resume January 3.

The Gantt shows the conservative November 25 start / 10-week working-duration baseline, targeting February 16, 2027. Depending on the actual start and duration, preliminary completion falls January 23–February 16, 2027. Trade dates and inspections are provisional.

PRELIMINARY FIELD PLAN

Today on Site

Scheduled activityLoading today’s schedule…
Trades involved—
Coming next—
Baseline turnoverFEB 16, 2027CO / owner handoff
Schedule8–10 WEEKSPlus 2-week holiday shutdown
Tasks complete0 / 36Tracked activities
Next hold pointSBA + DEPOSITRequired before mobilization
PRELIMINARY SCHEDULE

Preliminary Gantt

Task Progress Green — Completed Blue — In Progress
Activity
NOV 15NOV 28DEC 12DEC 25JAN 8JAN 21FEB 4
KEY MILESTONES

Opening-day path

PRELIMINARY ASSUMPTIONS

Before mobilization

01
Funding and deposit

Start remains conditional on SBA loan closing and deposit received.

02
Holiday shutdown

No field work or inspections from December 20 through January 2 inclusive.

03
Confirm the working schedule

Finalize trade availability, deliveries and inspection appointments when the start date is confirmed. The permit is issued.