LIVE FIELD UPDATE

Today on Site

Scheduled activityLoading today’s schedule…
Trades involved—
Coming next—
Target turnoverNOV 24CO / owner handoff
Schedule85 DAYSCompletion one week before December 1
Tasks complete0 / 36Tracked activities
Next hold pointOCT 22Underground plumbing
LIVE SCHEDULE

Critical path

Task Progress Green — Completed Blue — In Progress
Activity
SEP 1SEP 13SEP 25OCT 7OCT 20NOV 1NOV 13
KEY MILESTONES

Opening-day path

SCHEDULE CONTROLS

Protect the finish date

01
Inspection hold points

No backfill, concealment, or ceiling closure until approval. October 29 inspections are sequenced before drywall starts October 30.

02
Owner electrician coordination

Coordinate rough-in October 26–28 and inspection October 29. Concrete must be ready before framing October 25.

03
Coordinated finish work

Painting, flooring, and millwork follow the revised November sequence.

04
Rolling punch list

Close deficiencies as work proceeds—not at the end.