HVAC underway ahead of schedule
We have moved HVAC venting installation up from September 21st start to september 18th to ensure full mobility for HVAC techs prior to framing.
← All projects
Daytona Beach, Florida · Field work November 6 · Final inspections November 9–10 · November 14 deadline
We have moved HVAC venting installation up from September 21st start to september 18th to ensure full mobility for HVAC techs prior to framing.
Passed. We are clear to pour concrete
Termite Treatment Certificate issued today
Passed.
There has been a 1 week delay in getting the plumbing inspection done. First attempt, inspector did not read lock box notes. Second attempt, inspector cancelled, no reason given. 3rd attempt, administrative delay, city wanted plumbers updated license on file (updated license sent). Plumbing inspection now scheduled for September 10th. Soil compaction was completed. Waiting for plumbing sign-off so we can finish termite treatment, rebar and concrete pour. Job still on schedule.
The City of Port Orange has asked for plumbers updated master license. Updated license has been sent to city. Old license expired after project start date.
Plumbing Inspector cancelled inspection (unknown reason) rescheduled for Tuesday September 8th. Soil Compaction and termite treatment proceeding as scheduled.