CONSTRUCTION PROJECT TRACKER

BLO Daytona

Project on schedule

Daytona Beach, Florida · Field work November 6 · Final inspections November 9–10 · November 14 deadline

Overall completion74%
39 of 53 activities complete
PROJECT HEALTHLive project signals
ScheduleOn schedule
InspectionsElectrical rough inspection — November 3, 2026
Client decisionsNo action required
PROJECT RECORD

GC Notes

HVAC underway ahead of schedule

We have moved HVAC venting installation up from September 21st start to september 18th to ensure full mobility for HVAC techs prior to framing.

Slab/concrete Inspection

Passed. We are clear to pour concrete

Termite Treatment

Termite Treatment Certificate issued today

Plumbing First Inspection

Passed.

First Plumbing Inspection Update

There has been a 1 week delay in getting the plumbing inspection done. First attempt, inspector did not read lock box notes. Second attempt, inspector cancelled, no reason given. 3rd attempt, administrative delay, city wanted plumbers updated license on file (updated license sent). Plumbing inspection now scheduled for September 10th. Soil compaction was completed. Waiting for plumbing sign-off so we can finish termite treatment, rebar and concrete pour. Job still on schedule.

City of Port Orange administrative request

The City of Port Orange has asked for plumbers updated master license. Updated license has been sent to city. Old license expired after project start date.

Plumbing Inspection #1

Plumbing Inspector cancelled inspection (unknown reason) rescheduled for Tuesday September 8th. Soil Compaction and termite treatment proceeding as scheduled.